Completed Project

Proposition #2

Convention Center

$2,810,000

PROJECT COMPLETED AUGUST 2016

Bond program improvements, completed in August 2016, have transformed the Abilene Convention Center into a modern, versatile venue that will accommodate a wide range of events. A new lighting system, provides the exhibit hall a lively ambiance as well as greater energy efficiency. The computerized system can create millions of different colors, and the new LED lights last more than six times longer than the previous fluorescent bulbs did. The exhibit hall renovations also replaced the sound system and rehabilitated the walls, floors and kitchen.

The renovations also equipped the auditorium with an automated fly system, at left, to move curtains, lights and theater set pieces. The previous 50-ton counterweight fly system was nearly 45 years old and had to be operated manually.

 

  • STATUS DATE  DETAILS TARGET COMPLETION
    Complete Aug 22, 2016  Renovations completed - Ribbon Cutting!  
    Under Construction
    May 6, 2016   Construction begins Aug 2016
    Design Process Fall 2015 Design phase




    Work-In-Progress


  • STATUS DATE  DETAILS TARGET COMPLETION
    Complete  Aug 22, 2016  Renovations completed - Ribbon Cutting!  
    Construction  June 2016 Construction begins   Aug 2016
    Design Process  Fall 2015 Design phase begins. Construction is anticipated to begin in June 2016