Lake Abilene Dam Improvements

CIP FY 2024

Project Number: not yet assigned

Funding Source: Water Utilities Capital

Location: Off of Highway 89 about 24.5 miles south of Abilene located at Abilene State Park

Budget: $2,992,000 OPCC (Opinion of Probable Construction Cost)

Type: Dam Improvements

Start Date: 08/15/2022

Completion Date: 08/14/2023

Details: This project is minor maintenance and repairs to the embankment slopes, removal of vegetation, repairs to concrete structures, and resurfacing the dam crest.

Status: Design

       
ProgrammedFeasibilityPre DesignDesignBiddingConstructionCloseout

Last Project Update: 8/18/23

Project Contacts: 

  • Katherine Beeman, Project Manager 325-725-3415
  • Kent Hackworth, Project Inspector 325-725-3589