CIP FY 2024
Project Number: not yet assigned
Funding Source: Water Utilities Capital
Location: Off of Highway 89 about 24.5 miles south of Abilene located at Abilene State Park
Budget: $2,992,000 OPCC (Opinion of Probable Construction Cost)
Type: Dam Improvements
Start Date: 08/15/2022
Completion Date: 08/14/2023
Details: This project is minor maintenance and repairs to the embankment slopes, removal of vegetation, repairs to concrete structures, and resurfacing the dam crest.
Status: Design
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589