CIP FY 2024
Project Number: CB-2363
Funding Source: Water Utilities Cash Fund
Location: Hwy 83 from Summit Road to FM 3034 Exit 693
Budget: $508,310.00
Type: Water Line Replacement 7 Improvements
Start Date: October 1, 2023
Completion Date: TBD
Details: The removal of 8" pipe line and installation of 12" relocated outside TxDOT right of way to make room for a TxDOT highway expansion project.
Status: Bidding
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589