CIP FY 2023
Project Number: not yet assigned
Funding Source: Water Utilities Capital
Location: At the corner of South Danville and Brief Street
Budget: $220,000 OPCC (Opinion of Probable Construction Cost)
Type: Hydraulic and Capacity Demo
Start Date: Fall 2023
Projected Completion Date: Spring 2024
Details: This project is to fully abandon an aging pump station after the completion of the new Northwest Pump Station on Marigold Street. This new pump station will provide the pumping and flow capabilities for the system.
Status: Programmed
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589