Maple Street Pump Station

CIP FY 2027

Project Number: Not yet assigned

Funding Source: Water Utilities Capital

Location: Off of Maple Street and Loop 322 near Kirby Lake

Budget: $4,140,000 OPCC (Opinion of Probable Construction Costs)

Type: Hydraulic and Capacity Construction

Start Date: Fall 2026

Completion Date: TBD

Details: This project increases the 2nd Pressure Plane pumping capacity of Maple Street Pump Station from X million gallons per day to 21 million gallons per day, with the addition of a 3rd pump and replacement of existing pumps. The project includes construction of a new 2 million gallon Ground Storage Tank.

Status: Programmed

       
ProgrammedFeasibilityPre DesignDesignBiddingConstructionCloseout

Last Project Update: 8/18/23

Project Contacts: 

  • Katherine Beeman, Project Manager 325-725-3415
  • Kent Hackworth, Project Inspector 325-725-3589